MILESTONES

Project Timeline and Milestones

  • 2025

    New O’ahu Jail 2025 Milestones

    • Legislature approved funding of $30 million to continue new jail planning and development
    • Attended two American Correctional Association Conferences/Presentation at Orlando conference
    • Redesign eliminated community transition center as part of the new jail plan per community feedback. State plans to expand the existing Laumaka Work Furlough Center to house the transition center’s programs and residents.
    • Participated in roundtable discussion on PBS Insights
    • Presented the Public Private Partnership Project Delivery Model to key legislators
    • Completed conceptual design and moved to schematic design
    • Participated in the Aiea Holiday Parade and Fun Fair

  • 2024

     Advancing Communication and Finalizing Analyses

    • Published 5 OCCC newsletters (Vols. 51-55) through October (November pending approval)
    • Prepared for and attended American Correctional Association Conference (Nashville, TN)
    • Prepared for and attended Industry Networking Event (Nashville, TN)
    • Completed new Value for Money (VfM) Analysis for OCCC
    • Prepared updated OCCC Communications Plan
    • Expanded and maintained OCCC Master Contacts List
    • Attended monthly meetings of Hawai’i Correctional Systems Oversight Commission
    • New “Frequently Asked Questions” prepared
    • Community outreach and engagement
    • Value for money analysis update 
    • Cost estimate update 
    • Risk workshop

  • 2023

    Progressing Confirmation and Market Assessment

    • Published 4 OCCC newsletters (Vols. 47-50)
    • Plan Review Use Permit Annual Status report for Year 2023 submitted to Honolulu Department of Planning and Permitting
    • Posted 12 OCCC Outreach/Engagement Calendars (January to December) to OCCC website
    • Profile of “State of Hawai’i’s Construction Market”
    • Expanded and maintained OCCC Master Contacts List
    • Attended monthly meetings of Hawai’i Correctional Systems Oversight Commission
    • Community outreach and engagement 
    • Facility program confirmation 
    • Published 4 OCCC newsletters (vols. 47-50)

  • 2022

    Establishing Foundations and Expanding Outreach

    • Published 7 OCCC newsletters (Vols. 40-46)
    • Plan Review Use Permit Annual Status report for Year 2022 submitted to Honolulu Department of Planning and Permitting
    • Civil Utility Investigation for the Animal Quarantine Station Relocation, Final Report
    • OCCC and CTC Architectural Space Program Final Report
    • Sewer Connection Application Extension approved
    • Posted 12 OCCC Outreach/Engagement Calendars (January to December) to OCCC website
    • Public Benefit Conveyance Program Application to U.S. Department of Justice (for AQS property)
    • Expanded and maintained OCCC Master Contacts List
    • Attended monthly meetings of Hawai’i Correctional Systems Oversight Commission
    • OCCC “Program Statement of Probably Cost” prepared
    • Community outreach and engagement
    • Site plan confirmation
    • Value for money analysis
    • Published 7 OCCC newsletters (vols. 40-46)

  • 2021

    OCCC Request for Interest released

    • New O’ahu Jail Project] population forecast prepared 
    • Updated OCCC development program initiated 
    • Preparation of Request for Qualifications initiated 
    • Property easements and entitlements initiated 
    • Geotechnical and hazardous materials investigations completed 
    • Development plan for new Animal Quarantine Station prepared 
    • Published 12 OCCC newsletters (vols, 28-39)

  • 2020

    OCCC Plan Review Use application approved by City Council

    • OCCC boundary and topographic surveys prepared 
    • Final Environmental Assessments published for new housing units at MCCC, KCCC & HCCC
    • Published 4 OCCC newsletters (vols. 24-27)

  • 2019

    OCCC Master Plan completed

    • Plan Review Use application submitted to Department of  Planning and Permitting 
    • Draft Environmental Assessments published for new housing units at MCCC, KCCC and HCCC
    • Published 1 OCCC newsletter (vol. 23)

  • 2018

    Final OCCC Environmental Impact Statement published

    •  Governor Ige endorses OCCC development at Animal Quarantine Station. 
    • Legislature appropriates funds for new housing unit, administration building, visitation/intake building, and other improvements at WCCC
    • Planning and design of WCCC improvements initiated 
    • Published 6 OCCC newsletters (vols. 17-22)

  • 2017

    12 alternative OCCC sites identified and evaluated

    • Draft OCCC Environmental Impact 
    • Statement published (recommends developing [New O’ahu Jail Project] at Animal Quarantine Station site)
    • OCCC Community Partnering Plan developed
    • Published 10 OCCC newsletters (vols. 7-16)

  • 2016

    Planning for [New O’ahu Jail Project] begins with launch of site selection process

    • Preparation of OCCC population forecast
    •  Public outreach and engagement program
    • EIS studies, etc. 
    • Published 6 OCCC newsletters (vols. 1-6)

  • 2014

    Legislature appropriate funds for [New O’ahu Jail Project] planning.