The following were approaches considered for procuring proposals:
Design-Bid-Build (“low bid”)
- 89% of CIP procurement projects are low bid
- Projects are fully state funded
- Bid is prescriptive and specific
- State assumes full risk for due diligence, design and future maintenance
- Award is based on price
Design-Build
- For more complex projects: potential for innovative design and construction
- Fully state funded
- Performance specifications
- Award based on performance and price
- Developer assumed increased risk for design and construction
- More difficult to ensure owner’s expectations are met
- State assumes risk for future maintenance
Public-Private-Partnerships – Design-Build-Finance
- For more complex projects: potential for innovative design and construction
- Fixed state first cost; private financing for full scope
- Established future finance costs
- Performance specification
- Award based on performance, scope and future cost
- Developer assumes increased risk for design and construction
- More difficult to ensure owner’s expectations are met
- State assumes risk for future maintenance
Public-Private-Partnerships – Design-Build-Finance-Maintain
- For more complex projects: potential for innovative design and construction
- Fixed state first cost; private financing of full scope
- Established future finance and maintenance costs
- Performance specification
- Award based on performance, scope and future cost
- Developer assumes increased risk for design, construction and long-term maintenance
- Maintenance payments based on meeting performance specifications
- More motivation for developer quality control
- More collaboration to meet owner’s immediate and future expectations