Procurement Considerations

The following were approaches considered for procuring proposals:

Design-Bid-Build (“low bid”)

  • 89% of CIP procurement projects are low bid 
  • Projects are fully state funded 
  • Bid is prescriptive and specific 
  • State assumes full risk for due diligence, design and future maintenance 
  • Award is based on price 

Design-Build 

  • For more complex projects: potential for innovative design and construction 
  • Fully state funded
  • Performance specifications 
  • Award based on performance and price 
  • Developer assumed increased risk for design and construction 
  • More difficult to ensure owner’s expectations are met
  • State assumes risk for future maintenance 

Public-Private-Partnerships – Design-Build-Finance 

  • For more complex projects: potential for innovative design and construction
  • Fixed state first cost; private financing for full scope 
  • Established future finance costs 
  • Performance specification
  • Award based on performance, scope and future cost 
  • Developer assumes increased risk for design and construction 
  • More difficult to ensure owner’s expectations are met 
  • State assumes risk for future maintenance 

Public-Private-Partnerships – Design-Build-Finance-Maintain 

  • For more complex projects: potential for innovative design and construction 
  • Fixed state first cost; private financing of full scope 
  • Established future finance and maintenance costs 
  • Performance specification 
  • Award based on performance, scope and future cost 
  • Developer assumes increased risk for design, construction and long-term maintenance 
  • Maintenance payments based on meeting performance specifications 
  • More motivation for developer quality control 
  • More collaboration to meet owner’s immediate and future expectations